WEST has an interest
in Newcastle Mater Hospital:
|
Project Overview
· Redevelopment of Mater Hospital in Newcastle
NSW
· 26-year operating phase
· Three year, three stage construction
· Consortium:
Abigroup (D&C)
Medirest (Soft FM)
Honeywell (Hard FM)
· Availability based payments with no usage
risk
· Total financing costs c.$200 million
· Initial investment c.$21 million
Project Update
· Full construction completion reached in June
2009 in accordance with bid case development schedule
· Full service commencement on 1 July 2009 with
full service fee also commencing from July 2009
· Total abatements life to date have been
minimal and are passed through to subcontractors

For more information please visit the Newcastle Mater Hospital website.