WEST has an interest in Newcastle Mater Hospital:

 

Project Overview

·        Redevelopment of Mater Hospital in Newcastle NSW

·        26-year operating phase

·        Three year, three stage construction

·        Consortium:

     Abigroup (D&C)

     Medirest (Soft FM)

     Honeywell (Hard FM)

·        Availability based payments with no usage risk

·        Total financing costs c.$200 million

·        Initial investment c.$21 million

 

Project Update

·        Full construction completion reached in June 2009 in accordance with bid case development schedule

·        Full service commencement on 1 July 2009 with full service fee also commencing from July 2009

·        Total abatements life to date have been minimal and are passed through to subcontractors

 

Description: MtrNC-site_12-08_003 Description: MtrNC_air_Dec08_007

 

 

For more information please visit the Newcastle Mater Hospital website.